Your septic tank may be working perfectly, but what if the ground beneath your property cannot handle the wastewater? Before installing a drainage field, you need to know whether the soil can absorb effluent at a suitable rate. That is where a septic tank percolation test comes in.
The test focuses on the soil in your proposed drainage field area, not the septic tank itself. Its findings help you understand whether the ground is suitable for wastewater drainage and whether your installation plans need adjusting.
So, how do you carry out the test, calculate the Vp value and know whether your results are acceptable? This guide explains the process, suitable percolation values, drainage field sizing and your options if the ground fails the test.
What Is a Septic Tank Percolation Test?
A septic tank percolation test measures how quickly water soaks into the soil at the proposed drainage field depth. It helps establish whether the ground can absorb septic tank effluent while allowing further treatment as wastewater passes through unsaturated soil.
The result is expressed as Vp (percolation value), measured in seconds per millimetre. A lower Vp means faster infiltration, while a higher value indicates slower drainage. Excessively slow absorption can cause waterlogging, whereas overly rapid movement may limit natural pollutant removal.
According to the Environment Agency's guidance, percolation testing informs drainage field sizing and groundwater risk assessment. It does not establish site suitability on its own.
Is a Septic Tank Percolation Test the Same as a Soakaway Test?
No. Although both examine soil infiltration, they serve different purposes.
| Factor | Septic drainage field test | Rainwater soakaway test |
| Water type | Septic tank effluent | Rainwater |
| Design guidance | BS 6297 | BRE 365 |
| Result | Vp in seconds/mm | Infiltration rate |
| Purpose | Effluent disposal and treatment | Surface water disposal |
| Fast infiltration | Potential groundwater risk | Often favourable for drainage |
You cannot substitute a rainwater soakaway test for a foul drainage field assessment. England's general binding rules require suitable wastewater infiltration arrangements, not ordinary rainwater soakaways.
What Should Be Checked Before Carrying Out a Percolation Test?
Before testing soil permeability, you need to establish whether your proposed drainage field location is suitable. This involves two types of ground investigation:
- Trial hole: Reveals soil layers and groundwater conditions, including evidence of seasonal waterlogging.
- Percolation holes: Measure how quickly water infiltrates the soil at the intended drainage field depth.
You also need to check several site conditions:
- Groundwater level: Allow at least 1.2 metres between the drainage pipe invert and the seasonally highest groundwater level.
- Location restrictions: Check groundwater Source Protection Zones, particularly SPZ1, and nearby drinking water supplies.
- Surrounding environment: Assess watercourses, steep slopes, saturated ground and other environmental constraints.
- Soil variations: Consider changes caused by local geology, previous excavation or ground compaction.
Position test holes throughout the proposed drainage field area, as conditions elsewhere on your property may differ.
An acceptable Vp alone does not confirm suitability. Groundwater separation, environmental restrictions and site conditions must also meet the relevant requirements.
How to Carry Out a Septic Tank Percolation Test
A septic tank percolation test involves filling prepared holes with water and measuring how quickly the level falls. The procedure below follows the method described in England's drainage guidance.
1. Dig the Percolation Test Holes
Excavate at least two test holes, spaced across the proposed drainage field area. Each should have a 300 mm square base, extending 300 mm below the intended invert level of the drainage pipes.
Testing at this depth matters because surface soil may absorb water differently from the underlying layers receiving the effluent.
Remove loose material from each hole without compacting the exposed soil. If deeper excavation is necessary, seek professional advice on safe access and excavation support.
2. Pre-soak the Soil
Fill the bottom 300 mm section of each hole with at least 300 mm of clean water and allow it to drain overnight.
This initial soaking helps reduce the influence of unusually dry ground, which might otherwise absorb the first filling unusually quickly and distort your measurements.
3. Refill the Hole and Measure the 150 mm Water Drop
The following day, refill each test hole to a water depth of at least 300 mm. Use a measuring tape or marked measuring rod to monitor the falling water level.
- Allow the water depth to fall to 225 mm, then start your stopwatch.
- Continue timing as the water drains into the surrounding soil.
- Stop the timer when the depth reaches 75 mm.
- Record the elapsed time in seconds for the 150 mm fall.
4. Repeat the Measurements
Carry out at least 3 measured tests in each of the 2 holes, giving you a minimum of 6 readings.
Record the times separately, allowing the water level to fall sufficiently before refilling for each new measurement. You can then calculate the average Vp from the valid results.
If readings differ considerably between locations, investigate the variation rather than assuming the ground drains uniformly.
When Should You Avoid Conducting the Test?
Unusual weather can make the results unrepresentative of normal ground conditions.
- Heavy rainfall: Already saturated soil may produce unusually slow infiltration readings.
- Prolonged drought: Dry ground can behave differently from its normal moisture condition.
- Severe frost: Frozen soil can restrict water movement and distort measurements.
There is no single ideal month for every property. Choose representative conditions and account separately for seasonal groundwater levels when assessing site suitability.
How Do You Calculate the Vp Percolation Value?
Once you have recorded the water level drop, calculating the Vp percolation value is simple. Divide the time taken for the measured 150 mm fall by 150.

The result is expressed in seconds per millimetre (s/mm). A lower Vp indicates faster water infiltration, while a higher value means the soil absorbs water more slowly.
Suppose your test produces the following measurements:
- Recorded time: 4,500 seconds
- Water level drop: 150 mm
- Calculation: 4,500 ÷ 150 = 30
- Vp result: 30 seconds per mm
For the final design value, calculate Vp for each valid reading and take the average across the required tests. This representative figure helps determine the drainage field area needed for your property.
What Is a Good Percolation Test Result for a Septic Tank?
A suitable septic tank percolation test result depends on how quickly water infiltrates the ground and whether the site meets drainage field requirements.
| Vp result | What it indicates | What it means |
| Below 12 sec/mm | Very rapid infiltration | Outside both published ranges |
| 12 to below 15 sec/mm | Borderline result | Within Approved Document H range but below Environment Agency guidance |
| 15 to 100 sec/mm | Acceptable percolation range | Drainage field may be suitable, subject to site assessment |
| Above 100 sec/mm | Slow infiltration | Conventional drainage field generally unsuitable |
| Little or no drainage | Very poor infiltration | Further ground investigation needed |
Why Do Some Sources Say 12 to 100 and Others Say 15 to 100?
The difference comes from two official guidance documents used in England.
Approved Document H specifies an average Vp between 12 and 100 seconds per mm, provided the preliminary site assessment and trial hole findings are favourable.
The Environment Agency's groundwater risk assessment guidance uses 15 to 100 seconds per mm for infiltration systems.
A result between 12 and 15 seconds per mm is therefore not an automatic pass. You need to establish which requirements apply to your proposed installation, including whether an environmental permit or further groundwater assessment is necessary.
Why Can Ground Drain Too Quickly?
Fast drainage might seem beneficial, but septic tank effluent needs sufficient contact with unsaturated soil for further treatment.
Highly permeable sand, coarse gravel or fractured rock can allow wastewater to travel rapidly towards groundwater. This limits the time available for natural processes to reduce contaminants.
Where Vp falls below 15 seconds per mm, the Environment Agency identifies a risk of insufficient pollutant attenuation. Such conditions may require an alternative treatment or infiltration design.
Why Can Ground Drain Too Slowly?
Poor infiltration often occurs where clay-rich subsoil, compaction or restricted soil structure limits water movement. High groundwater levels can make the problem worse.
When effluent enters the drainage field faster than the soil can absorb it, wastewater may accumulate underground, rise towards the surface or cause drainage problems upstream.
Clay soil does not automatically mean failure. Its structure, depth and actual test results determine whether infiltration is adequate. A Vp above 100 seconds per mm generally indicates that a conventional drainage field is unsuitable
How Is the Percolation Test Used to Size a Drainage Field?
Your percolation test result helps determine how much drainage trench area is needed to disperse wastewater from your septic tank. The calculation considers both the soil's infiltration rate and the number of people the system must serve.
Septic Tank Drainage Field Formula
For septic tank effluent, the drainage field sizing formula is:
A = p × Vp × 0.25
Where:
- A: Required drainage trench floor area in square metres (m²).
- p: Design population, based on the maximum number of people the property is designed to accommodate.
- Vp: Average percolation value in seconds per millimetre.
For example, suppose your property has a design population of six people and an average Vp of 30 seconds per mm.
Drainage field area = 6 × 30 × 0.25 = 45 m²
This means you need 45 square metres of drainage trench floor area.
If each trench is 600 mm (0.6 m) wide, calculate the total trench length as follows:
Total trench length = 45 ÷ 0.6 = 75 metres
You would therefore need a total of 75 linear metres of drainage trench.
This is an illustrative calculation, not a complete drainage field design. The final layout must also account for trench spacing, available land, groundwater conditions and other site requirements.
For effluent receiving secondary treatment from a sewage treatment plant, the sizing coefficient changes to 0.20 instead of 0.25.
What Happens if a Septic Tank Percolation Test Fails?
A failed percolation test does not necessarily mean you cannot install an off-mains wastewater system. Your next steps depend on whether the ground absorbs water too quickly or too slowly.
| Test outcome | Potential problem | What you can do |
| Ground drains too quickly | Effluent may reach groundwater without adequate treatment | Investigate an engineered drainage mound, sand filter or suitably designed infiltration system |
| Ground drains too slowly | Wastewater may accumulate because the soil cannot absorb it adequately | Assess another location, investigate ground conditions or consider an alternative discharge arrangement |
| Little or no infiltration | Conventional drainage field disposal may be impractical | Seek professional ground investigation and assessment of other lawful wastewater solutions |
For excessively rapid infiltration, simply increasing the drainage field size will not address the groundwater pollution risk.
Engineered solutions require professional design. England's general binding rules permit certain drainage mounds and engineered ground arrangements where the specified design, location and construction requirements are met.
If the soil drains too slowly, installing a sewage treatment plant does not automatically resolve the problem. Even treated effluent needs a suitable discharge route, whether that involves an appropriately designed drainage field or another legally permitted arrangement.
Can You Repeat the Percolation Test Somewhere Else?
Yes. You can investigate another part of your property if you genuinely intend to install the drainage field there.
Soil permeability can vary considerably across a site, meaning one location may produce different results from another. Any alternative area must still meet the relevant groundwater separation, environmental, space and drainage design requirements.
A successful test elsewhere does not make the original failed location suitable. The results must represent the ground where the drainage field will actually be installed.
Does Passing a Percolation Test Mean You Can Install a Septic Tank Drainage Field?
No. A suitable percolation test result confirms that the soil absorbs water at an acceptable rate, but it does not guarantee that your proposed drainage field can be installed.
Before proceeding, you must also consider:
- Groundwater conditions: Sufficient separation between the drainage pipes and the highest seasonal groundwater level.
- Available space: Enough land to accommodate the required drainage trenches and their spacing.
- Separation distances: Adequate clearance from buildings, property boundaries, watercourses and drinking water sources.
- Treatment capacity: A septic tank or sewage treatment plant sized for the property's expected wastewater demand.
- Site suitability: Ground stability, flood risk and other environmental constraints.
- Installation approval: Applicable planning permissions, Building Regulations and environmental requirements.
A successful test is only one part of the assessment. The complete drainage field design must be suitable for your property's conditions before installation can proceed.
Should You Do a Septic Tank Percolation Test Yourself or Use a Professional?
You can perform a septic tank percolation test yourself, provided you follow the correct procedure and take accurate measurements. The difficulty comes when you need to establish what those results mean for your proposed drainage field.
If the readings are consistent and ground conditions are uncomplicated, the measurements may be relatively simple to obtain. Professional input becomes more important when the results vary between holes, groundwater levels are uncertain or there is limited space for drainage trenches.
Properties with clay, rock or previously disturbed ground may also need further investigation. The same applies when Vp values are borderline or an engineered drainage mound is being considered.
A drainage specialist can assess the findings alongside the property's conditions and prepare a design supported by the necessary evidence, particularly when Building Control, planning approval or an environmental permit is involved.
Get Your Drainage Field Design Right From the Start
A septic tank percolation test gives you valuable information before you invest in drainage field construction. The Vp result helps establish the required drainage area, but groundwater conditions, available space and installation requirements can still affect your plans.
If your readings are inconsistent, borderline or outside the acceptable range, seeking professional advice early can help you avoid unsuitable installations and costly alterations later.
At Drain Surgeons, we provide professional septic tank services, sewage treatment plant installation and servicing, and private drainage solutions. Whether you're planning a new wastewater system or need help with an existing installation, our team can assess your drainage requirements and recommend a suitable approach.
Contact us to discuss your property and find out which drainage solution best meets your needs.
FAQs
How deep should a septic tank percolation test hole be?
The testing section should be 300 mm deep below the proposed invert level of the drainage field pipes. The total excavation depth depends on how deep the pipework will sit. For deeper installations, you may need a larger excavation above the testing section to maintain safe working conditions.
How many holes do you need for a percolation test?
You need at least two percolation test holes positioned across the proposed drainage field area. Each hole should undergo at least three measurements, producing a minimum of six readings. Larger sites or locations with inconsistent ground conditions may require more holes to obtain representative results.
How long does a septic tank percolation test take?
Allow at least two days for the basic procedure, including overnight soil soaking. The actual measurement period depends on how quickly water infiltrates the ground. Additional time may be needed for excavation, repeated readings and groundwater investigations, particularly where the soil absorbs water slowly.
Can you install a septic tank if the percolation test fails?
A failed test does not necessarily prevent you from installing a septic tank, but it may rule out your proposed drainage field. You will need to establish a suitable, lawful route for wastewater disposal. Installing a tank without an acceptable discharge arrangement is not a solution.
Does a sewage treatment plant need a percolation test?
Yes, if the treated wastewater will discharge into a drainage field. Although a sewage treatment plant provides more treatment than a conventional septic tank, the receiving soil must still be suitable for infiltration. A percolation test is not normally needed for a permitted direct discharge to a watercourse, although other assessments may apply.
Can you do a percolation test in clay soil?
Yes. Clay soil can be tested using the same procedure, although water may infiltrate slowly because of its low permeability. Some clay soils have better drainage characteristics than others. The measured results, soil structure and groundwater conditions will determine whether the proposed drainage field is feasible.
Can you redo a failed percolation test?
Yes, particularly if the original measurements were affected by unusual weather, incorrect preparation or inconsistent testing methods. You should establish why the first test failed before repeating it. Retesting under more favourable conditions simply to obtain a passing result would not provide reliable evidence of site suitability.
What is the difference between a trial hole and a percolation test hole?
A trial hole is a larger excavation used to examine soil layers and investigate groundwater conditions. A percolation test hole is smaller and designed to measure how quickly water enters the surrounding soil. Both investigations provide different information needed to assess a proposed drainage field.